Berlin developer Townscape has commenced construction work on a new serviced apartment scheme in Berlin-Kreuzberg. Following planning permission granted in April 2026 and preparatory site works, the excavation pit on the roughly 1,100 square metre site at Prinzessinnenstrasse 29 has been fully dug. In the next construction phase, work will begin on the building's foundations.
Completion of the new building is scheduled for the third quarter of 2027. In total, 114 serviced apartments are being built across a planned gross floor area of around 3,700 square metres. The concept envisages extending the short-stay residential offering on the ground floor with complementary commercial and co-working space. numa group SE has been confirmed as the tenant for the entire property.
Established environment in Kreuzberg's creative quarter
The site is located close to Moritzplatz in the heart of an established creative district. The immediate surroundings are shaped by institutions such as the Aufbau Haus with its art, cultural and social facilities, as well as the Prinzessinnengärten. With Betahaus, one of the traditional co-working hubs of Berlin's creative scene is also situated in the immediate vicinity, flanked by food and drink venues.
In terms of infrastructure, the site also benefits from strong transport connections. The Moritzplatz and Kottbusser Tor underground stations are within walking distance, whilst private transport is linked via Prinzenstrasse and Oranienstrasse. Local recreation spots such as the Engelsbecken and the Landwehr Canal are also located nearby.
Construction progress
Nilgün Dusny, responsible project manager at Townscape, stated at the start of construction that the excavation of the pit represented an important milestone. Following the scheduled completion of preparatory measures, the company is now looking ahead to the upcoming foundation works. She added that the scheme enhances the location with a contemporary hospitality offering, which will be delivered over the coming months in close partnership with project partners and tenant numa group.
- —Site area: around 1,100 m² at Prinzessinnenstrasse 29
- —Planned gross floor area: around 3,700 m² with 114 units
- —Occupier: numa group SE for serviced apartments, commercial and co-working space
- —Completion timeframe: third quarter of 2027