Project launch on the Kassel Airport site
On an approximately nine-hectare brownfield redevelopment site at Kassel Airport in Calden, project developer Panattoni and the technology and defence group Rheinmetall have performed the symbolic ground-breaking ceremony for a combined logistics and training centre. The so-called Defence Hub represents one of the group's largest current infrastructural construction projects in Germany.
Two building complexes with a combined usable space of around 38,000 square metres will be built on the site by the end of June 2027. The spatial focus is a logistics centre of around 31,100 square metres, which will serve in future as a central hub for materials, storage, transhipment and dispatch. Directly adjacent, a training centre spanning around 6,900 square metres is being constructed. The project combines logistical supply with on-site practical training capacity and is expected to create up to 200 jobs in the long term.
Industrial consolidation and coordinated schedule
The State of Hesse and Rheinmetall are jointly investing a three-digit million-euro sum in the site to purposefully expand North Hesse as a centre of competence for defence technology. Dr Till Kaesbach, State Secretary in the Hessian Ministry of Finance and Chairman of the Supervisory Board of Kassel Airport, underlined the importance of the relocation for long-term value creation and the airport's economic future. In the long term, the establishment of a testing centre for drones is also planned on the site.
According to Dr Björn Bernhard, CEO of the Vehicle Systems Europe division and Managing Director of Rheinmetall Landsysteme GmbH, growing demand for systems and vehicles requires expanded space for rapid materials turnover and targeted training of specialists. Fred-Markus Bohne, Managing Partner at Panattoni DACH & Nordics, highlighted the need for robust structural infrastructure for operational defence readiness capable of satisfying complex security and user requirements.
Physical handover is targeted for the end of June 2027, with operational activity due to commence towards the end of that year. Calden's mayor Maik Mackewitz emphasised the momentum behind the implementation, noting that only three months elapsed between the public location decision and the official start of construction, and that earthworks across the construction site are already well advanced.
- —Site: Around 9 hectares of brownfield conversion land at Kassel Airport in Calden
- —Usable area: Approximately 38,000 sq m (31,100 sq m logistics, 6,900 sq m training centre)
- —Investment: Three-digit million-euro sum from the State of Hesse and Rheinmetall
- —Schedule: Handover planned for end of June 2027, operational launch at the end of 2027