Developer SEGRO has announced the completion of the first two logistics properties at SEGRO Park Dortmund. Together, the two structures comprise a lettable area of around 56,000 square metres and mark the first construction milestone on the former power station site in the Ruhr region.
A major part of this completion is Building C, providing usable space of approximately 37,300 square metres. The property has been fully and long-term let to global healthcare company Cencora, which offers services to pharmaceutical manufacturers, pharmacies and healthcare providers. According to Christian Pieper, Managing Director DACH at Cencora, the lease represents an important step in expanding the firm's market presence in Germany whilst also supporting its objective of organising operations more sustainably.
In the immediately adjacent Building A, around 18,500 square metres of logistics space are available for lease with immediate effect. According to Julian Kux, Director Logistics at SEGRO in Germany, this new building is characterised by flexible adaptation options for various operational models and accommodates sophisticated logistics processes. Kux emphasised that the location is designed to serve diverse requirements ranging from large-scale contract logistics and light industrial use to urban logistics concepts.
Major pre-let to Amazon and expansion by mid-2027
Alongside the completed units, SEGRO is advancing the delivery of Building B. This large-scale property, offering around 86,400 square metres of space, was already fully let to Amazon prior to the start of construction. Completion of this development phase is scheduled for mid-2027.
The entire site covers 60 hectares on the grounds of a former coal-fired power station in north-western Dortmund, directly on the city boundary with Castrop-Rauxel. The location benefits from direct connections, as the Castrop-Rauxel-Ost motorway junction serving the A42 and A45 motorways is just three minutes away. Following its final expansion, the business park is set to offer more than 200,000 square metres of warehouse space.
Ecological standards and amenity quality
During the revitalisation of the former industrial site, the developer is implementing extensive sustainability measures. In addition to resource-efficient construction methods designed to reduce the carbon footprint, green roofs and large-scale photovoltaic systems are planned. The solar installations on the warehouse roofs are intended to generate a total capacity of more than 10 megawatts. In addition, recreation and break areas for park employees as well as designated rest zones for lorry drivers are being created.
- —Total site area of 60 hectares on a former power station site
- —Around 56,000 square metres of lettable area completed in the first two buildings
- —Long-term lease for 37,300 square metres secured with Cencora
- —Full letting of 86,400 square metres in Building B to Amazon with completion by mid-2027
- —Planned photovoltaic installations with more than 10 megawatts peak capacity