Loudoun County in the US state of Virginia, the location with the highest density of data centres in the world, has approved a twelve-month freeze on approvals for new server parks and substations. The county's Board of Supervisors voted 7 to 1 in favour of the measure on Tuesday evening, with one abstention. The purpose of the pause is to fundamentally overhaul the planning framework for this rapidly expanding asset class.
The decision applies retroactively to 15 September, the day the administration was first instructed to draw up the resolution. Although developers can continue to submit applications, their review by political bodies will be suspended for up to twelve months from receipt by the relevant planning commission. During this period, the administration aims to define new location criteria and urban design requirements for digital infrastructure.
Affected projects and exemptions
The moratorium currently affects 33 pending applications for data centres and substations that require special planning permissions. According to reports, however, around 15 to 17 projects submitted under earlier regulations or benefiting from grandfathering protections can proceed as planned. Furthermore, new substations strictly required for power grid stability as well as selected redevelopments along the Route 28 corridor are exempt from the freeze.
The delays are expected to cause a significant application backlog once the period expires. The administration anticipates that clearing the deferred applications from autumn 2027 will require additional hearings over a period of four to six months. Developers criticised the decision, pointing out that such a postponement damages institutional investor confidence and puts existing planning at risk. In addition, legal challenges are being considered.
Growing concerns despite high tax revenues
The decision marks a clear turnaround for Loudoun County, which actively encouraged the industry to locate there over a period of two decades. The county is home to around 253 data centres with a total floor area of 49 million square feet, representing approximately a quarter of total US capacity. These facilities generate 1.3 billion dollars in local tax revenues for the county each year.
However, the surge in demand triggered by artificial intelligence applications has raised significant reservations among the public. Criticism focuses on the immense power demand, high land consumption and increasing proximity to residential areas. Loudoun had already abolished simplified approval procedures without special review in March 2025. Neighbouring regions are also taking action: Prince William County tightened its zoning rules in September, while Montgomery County imposed an 18-month moratorium in July.