The logistics centre developed by ID Logistics Germany in the greater Aachen area, specifically in Alsdorf, commenced operational activities on 4th August 2026. Commissioning took place on schedule after a three-month conversion phase. From this geographically central location in the Germany-Netherlands-Belgium tri-border region, the supply of fulfilment and distribution centres for a major e-commerce retailer will be coordinated.
Leif Venus, Director Last Mile & Specialized E-Commerce at ID Logistics, confirmed the start of goods intake at the logistics facility. The volume of goods to be handled will be progressively increased. It is predicted that up to 50,000 parcels per day can be handled, stored, or retrieved in the multifunctional property. The ramp-up of operations is aligned with the client's requirements.
Revitalisation of an existing property
The total area of the eight halls, comprising 72,800 square metres, is scheduled to be fully operational in four sections by the second quarter of 2027. Robin Otto, CEO of ID Logistics Germany, emphasised that an already used industrial area was revitalised and specifically developed further within a short period. This enabled the property to be brought into a new usage cycle as required. Otto highlighted that intelligent planning in Alsdorf can create future-proof logistics locations without additional land sealing.
A significant advantage of this existing property development is the realisation time. In contrast to new-build projects, existing property developments are less dependent on construction progress. According to Otto, development times for existing properties can often be reduced by 70 to 90 percent compared to classic new-build projects. Technical and intralogistic expansion continues in parallel with the operational ramp-up.
Technological equipment and personnel development
The storage concept for time-critical online retail combines capacities for unpalletised and palletised goods. ID Logistics Germany invested in high-bay and narrow-aisle systems, forklifts, and conveying technology. A central role is played by 45 special industrial trucks, known as man-up trucks, which allow operating personnel to pick goods directly from high-level rack compartments. Digital control and monitoring of warehouse movements are carried out via a Warehouse Management System, which ensures continuous transparency and efficient inventory management.
- —Test phase: A three-week test phase preceded commissioning.
- —Process optimisation: Storage strategies, fill levels, and all process steps from lorry handling to quality control were tested under real conditions.
- —Standardisation: The tested procedures were converted into standardised processes.
The team at the site will be gradually expanded in parallel with the operational ramp-up. Currently, approximately 65 employees are working in Alsdorf. With the successive commissioning of further halls, an increase in the number of employees to a total of around 300 jobs is planned.